10,000 Home Sites Program: update as at 30 September 2013

22 July 2014
  • Our production program was ahead of target by 256 homesites at the end of September. This will drop to around 66 lots ahead of target in October and we then forecast it to rise to about 150 homesites ahead of target for the following six months.
  • There has been a substantial recent increase in market demand, particularly in the south west, which has reduced stock levels across the portfolio. In response, we are accelerating production across all our projects.

Currently in production

Over the next six months, UrbanGrowth NSW will release 1,241 home sites, as detailed below:

There is significant construction activity across all of our projects, with about 1,630 home sites under construction.

News and insights

Related articles

Work starts on Greater Sydney’s newest suburb

Work on Greater Sydney’s newest suburb has begun with the first sod turned at Landcom’s North Wilton development, paving the way for more than 5,000…

9 Feb 2023

Green light for Macarthur Gardens North Project

Landcom is expected to start work in April 2023 after receiving development approval for the Macarthur Gardens North project.

20 Jan 2023

5,700 new homes to transform Sydney's Northwest

Sydney’s Northwest will be transformed with around 5,700 new homes and new community spaces and facilities after plans for the future of Bella Vista Station…

2 Dec 2022
Sign up

Get the latest news

Stay up to date on insights into our plans, projects and partnering opportunities