Construction and planning updates
Stage 4B: Construction has commenced for 51 residential lots inclusive of 14 social lots. Works are anticipated to be completed by April 2024.
Stage 9: Stormwater drainage, earthworks and water supply works are progressing on site. This stage is on track for completion by mid-2024.
Riley Park: Civil works continue on site for 20 residential lots inclusive of five social lots with works scheduled for completion by April 2024.
Towner Avenue
Construction of the western part of Towner Avenue is complete, linking St John’s Road and Partridge Street. This section of road will open to the public following approval from Council, which we hope to get in April 2024. Works to complete the eastern part of Towner Avenue are expected to commence in mid-2024 and will connect Partridge Street and Riverside Drive, south of the Newbrook Shopping Village.
Kevin Wheatley Reserve
Following the fire, the design of the stormwater tank for Kevin Wheatley Reserve is being revised with works aiming to recommence by mid-2024. On completion, the Kevin Wheatley Reserve will feature two full-sized soccer fields with synthetic grass and lights, a new amenities building, a playground and a half-court basketball court.
The Pond
Works on the Pond reserve have recommenced with the completion of earthworks and progression of the stormwater drainage. The upgraded Pond will include a larger water reserve, new landscaping and paths, seating and a new playground.